Feasibility for a Small Residential Development: The Arithmetic Before the Architect
A scheme is viable or it is not, and the answer is usually visible before a single drawing is produced. Here is the calculation, in the order that matters.

Feasibility is not a mood. It is a short, honest calculation that answers a single question: if we build this, will the finished value exceed the cost of the land, the construction, the professional team, the finance and the risk? Everything else — design, planning strategy, marketing — follows from that answer.
Most small developers do the calculation backwards. They fall in love with a site, commission a scheme, obtain a quote and then try to make the numbers work by trimming specification. The result is a project that was never viable and is now also badly built. The order matters: value first, cost second, land price last.
The short version
- Start with achievable sales value, not with the asking price of the land.
- Use a fully loaded build cost per square metre, including externals, utilities and site overheads.
- Residual land value is the number that decides what you can pay, not what the agent hopes.
- Stress-test the scheme at lower value, higher cost and longer programme.
- If the margin disappears under a modest stress, the scheme is marginal, not viable.
Step one: define the output precisely
You cannot value or cost a scheme that is still vague. Fix the number of units, the gross internal area of each, the tenure, the parking, the garden or amenity space and the specification level. A three-bedroom house of 95 square metres in a mid-market suburb is a different product from a four-bedroom house of 140 square metres on the same plot, and the difference changes both value and build cost.
Use comparable sales, not asking prices. Adjust for condition, garden size, parking, school catchment and the recency of the sale. A good valuer will give you a range and explain the adjustments. For feasibility, use the lower end of the range. Optimism belongs in the marketing plan, not the appraisal.
Step two: build cost, fully loaded
Construction cost is not the price a builder quotes for the superstructure. It includes demolition, site clearance, foundations, drainage, external works, services connections, landscaping, fencing, a show home or marketing suite if needed, and site management. It also includes the cost of the money while you build.
For a small residential scheme, a sensible early-stage figure is a rate per square metre applied to gross internal area, with additions for abnormal foundations, retaining walls, contaminated soil, restricted access or a conservation area. Then add a contingency of 10 to 15 percent. Small schemes need the higher end because there are fewer units over which to spread a surprise.
Professional fees typically include architect, planning consultant, structural engineer, energy assessor, building control, party wall surveyor, project manager and legal. On a small scheme these can reach 10 to 15 percent of construction cost. Finance costs depend on the loan-to-value, the interest rate and the programme. Short programmes flatter returns; realistic ones protect you.

Step three: the residual land value
Residual land value is what remains after you subtract all costs and your required profit from the gross development value. It is the maximum you can pay for the land and still hit your target.
Take a scheme with two houses, each worth 320,000, giving a gross development value of 640,000. Build cost is 1,100 per square metre across 190 square metres, or 209,000. External works and connections add 35,000. Professional fees at 12 percent of construction add 25,000. Contingency at 12 percent adds 25,000. Finance and legal add 30,000. Selling costs at 2 percent add 13,000. Total cost before land is 337,000.
If your target profit is 20 percent of gross development value, that is 128,000. Residual land value is therefore 640,000 minus 337,000 minus 128,000, or 175,000. That figure includes acquisition costs such as stamp duty and legal fees, so the headline offer must be lower still.
| Line | Amount |
|---|---|
| Gross development value | 640,000 |
| Construction and external works | 244,000 |
| Professional fees | 25,000 |
| Contingency | 25,000 |
| Finance, legal and selling | 43,000 |
| Target profit | 128,000 |
| Residual land value | 175,000 |
If the site is asking 240,000, the scheme does not work at that specification and profit target. You can change the specification, the unit mix, the programme or the profit expectation, but you cannot argue with the arithmetic.
Step four: sensitivity, not certainty
A single appraisal is a guess with a spreadsheet. Run at least three stress cases: sales values 10 percent lower, construction costs 10 percent higher, and the programme three months longer. Then combine them. A scheme that survives each individually but fails when two occur together is more fragile than it looks.
Pay particular attention to the profit margin expressed as a percentage of cost, not just of value. Developers often quote margin on gross development value because it looks larger. Lenders and investors increasingly look at return on cost, and the difference matters when you are borrowing.

Step five: planning risk
Feasibility without planning probability is fiction. Check the local plan allocation, the precedent for similar schemes within a reasonable radius, conservation area or green belt constraints, flood risk, access and parking standards, and any affordable housing or community infrastructure contribution that applies. A scheme that needs an exception to policy should carry a higher contingency and a longer programme.
Pre-application advice is often worth the fee. It does not guarantee consent, but it identifies the issues that would otherwise emerge after you have spent money on a full application. Speak to a planning consultant who has actually delivered in that authority, not one who promises a result.
Step six: the go/no-go decision
Set your criteria before you see the site. For example: residual land value at least 15 percent below the asking price, profit on cost above 20 percent after stress, planning risk assessed as moderate or better, and funding confirmed. If the site fails two criteria, walk away. The discipline is easier when the rules are written down in advance.
The land price is the variable that absorbs everyone else's optimism. It is also the only number you can negotiate before you are committed.

Common feasibility mistakes
- Using asking prices as comparables and ignoring condition adjustments.
- Forgetting external works, utilities, drainage and landscaping.
- Underestimating professional fees and the cost of finance.
- Applying a contingency meant for a large scheme to a two-unit project.
- Assuming the current programme will hold through planning and construction.
- Treating profit as a residual rather than a requirement.
What good looks like
A good feasibility fits on two pages, states its assumptions, shows the residual land value and includes a sensitivity table. It is revisable when a quote or a planning response arrives. It is not a marketing document for the project; it is a decision tool that can tell you to stop.
If the numbers work with room to spare, the scheme has earned its next stage: a proper design team, a measured survey and a cost plan. If they only work with optimistic inputs, you have saved yourself the most expensive lesson in development.

A final check before you commit
Confirm the title, access rights, services and any restrictive covenants before you exchange. A viable scheme on a site you cannot legally develop is not viable. Spend the legal fee early; it is cheaper than a stalled project.
Then write down the three assumptions that would most damage the scheme if they were wrong, and decide how you will test each one in the next thirty days. Feasibility is not a document you finish. It is a position you keep updating until the first shovel goes in.